Determine to open Hoa Lien - Tuy Loan Expressway by August 19
Deputy Minister of Construction Nguyen Viet Hung requested that investors and contractors adhere strictly to the construction timeline, maintain strict quality control, and ensure the Hoa Lien - Tuy Loan expressway is open to traffic by August 19.
On May 14th, Deputy Minister Nguyen Viet Hung and the Ministry’s delegation inspected the construction of Hoa Lien - Tuy Loan Expressway.

The Deputy Minister listened to the report on the current construction progress of Hoa Lien - Tuy Loan Expressway.
Deputy Minister Nguyen Viet Hung recognized and praised investors and contractors for their efforts in implementing the project.
The Deputy Minister also noted that the project is now in its critical phase, nearing completion, and that key issues concerning site clearance and construction materials need to be promptly addressed.
The Project Management Unit of Ho Chi Minh Road along with contractors need to continue the spirit of "overcoming harsh weather conditions", "3 shifts, 4 crews" to closely follow the schedule, maintain quality control, and ensure the project’s opening by August 19, in celebration of the 80th anniversary of National Day and the 80th anniversary of the transportation sector’s traditional day.
"The investors and contractors should proactively coordinate with local authorities to resolve issues within May and complete the connecting roads by November," the Deputy Minister instructed.

The Hoa Lien - Tuy Loan Expressway is scheduled to open to traffic on August 19th.
According to the report from the Ho Chi Minh Road Project Management Unit, the project is currently about 60% complete, focusing on tasks such as roadbed excavation; embankment construction at K95 and K98; laying graded crushed stone and various types of asphalt concrete, basically meeting requirements.
Following directives from the Prime Minister and leadership of the Ministry of Construction, the Project Management Unit has instructed relevant units and contractors to revise the schedule and maintain high determination to achieve the target of opening the expressway by August 19 and completing the entire project by November 2025.